How Long Does Interior Decorating Take? A Room-by-Room Guide

January 20265 min read

One of the first questions homeowners ask is how long will it take? Realistic timeframes help you plan around the disruption and know when to expect your home back to normal. Here is an honest room-by-room guide based on real jobs we carry out across York.

How Long Does Each Room Take?

RoomWalls & ceiling onlyWalls, ceiling & woodwork
Single bedroom0.5–1 day1–1.5 days
Double bedroom1 day1.5–2 days
Master bedroom1–1.5 days2 days
Living room1–1.5 days2–2.5 days
Kitchen0.5–1 day1–1.5 days
Hallway & stairs1–1.5 days2–2.5 days
Bathroom0.5–1 day1 day

Full House Repaints — Realistic Timelines

PropertyWalls & ceilingsFull redecoration
1-bed flat2–3 days3–5 days
2-bed house3–4 days5–7 days
3-bed semi4–6 days7–10 days
4-bed detached6–8 days10–14 days

What Makes Decorating Take Longer?

  • Poor surface condition — filling, sanding and priming bare patches adds significant time
  • High ceilings — Victorian properties in York often have 9–10ft ceilings which take longer
  • Ornate coving and cornices — period features require careful cutting in
  • Multiple colours — more masking and cutting in time per room
  • Wallpaper stripping — removing old paper before painting can add a day per room
  • Drying time — coats need to dry fully before the next is applied

Tips to Speed Things Up

  • Clear rooms of small items before the decorator arrives
  • Decide on colours before work starts — changes mid-job add time
  • Ensure good ventilation to help paint dry faster
  • Book well in advance so work can start promptly